June 21, 2016 Update (From Lisa Smith - City of Boulder Community Vitality )

 

  • JE Dunn has completed expected road work and the partial closure of Pearl Street has been opened
  • JE Dunn continues with finishing exterior work and anticipates the fence coming down around the July 4th weekend
  • Interior finish work by a variety of firms will continue at JE Dunn in coming months
  • Crews will be working in the West End to correct some stonework at 10th and Pearl this Wednesday and Thursday
  • The crews will remove the stones to recut them, cut them off site, and reinstall them
  • Since stone cutting will take place off-site, we do not anticipate loud demolition noise or disruption, e.g. from saw cutting
  • Business access will be preserved throughout but there may be some overnight fencing around places where stonework has been removed for safety reasons

If you have any questions related to Pearl West, please contact Adam Riggs at Adam.Riggs@jedunn.com.

If you have questions related to the stonework, please contact Lisa Smith at SmithL@bouldercolorado.gov.

 

June 2, 2016 Last Minute Update (From Scott Pashman - JE Dunn by Terri Takata-Smith - Downtown Boulder)

Within the last hour, we just received an update from JE Dunn.  On Monday, a contractor will be here to set the fourth floor trellis steel at PearlWest.

This will require six parking spaces - the six that are starting closest to Pasta Jay's and moving east (basically to Ozo) to be blocked off due to outriggers being past the center line of the road.    JE Dunn is anticipating that the six spaces will be blocked off for three days but promised to provide an update if that goes longer.

Please note this information was not included in the update sent earlier by the city because it was a very last minute change of plan.   We are letting you know as soon as we found out.

Please let me know if you have any questions and I'll put you directly in contact with someone from JE Dunn. Thanks.

 

June 2, 2016 Meeting Recap (From Scott Pashman - JE Dunn by Lisa Smith - City of Boulder Community Vitality)

Thank you to everyone who was able to attend JE Dunn's construction update meeting yesterday at Centro. I have confirmed the details of the street paving work that will begin next Monday:

  • JE Dunn will start road work on Pearl Street between 11th and 10th Streets this coming Monday June 6, 2016.
  • Crews will be working on the road on the south side of Pearl, the intersection of 11th and Pearl and the west lane of 11th.
  • Pearl Street will be taken down to one lane (the north lane) in this section in order to work on the lane on the south side of Pearl.
  • A portion of the intersection at 11th and Pearl Street as well as the west lane of 11th Street will be closed in order to complete this road work.
  • The work should take about two weeks to complete, weather permitting.
  • Starting Monday, you will see signage regarding the work and yellow cones on the north side of the double yellow line on Pearl.
  • Business access will be preserved.
  • The pedestrian walkway between Pearl and Walnut will remain open.
  • The HOP bus route will be rerouted to avoid the work site.  All eastbound traffic along Pearl will be detoured north on 10th.
  • There will be some parking impacts related to safety, but wherever possible parking will be preserved during work.
  • Some work will be conducted at night and at times weeknight overnight closures may be necessary; all such closures will start after 10 p.m. and end before 7 a.m.
  • Fencing around the Pearl West site is anticipated to come down permanently around July 4th.
  • We will send regular updates as we receive more information regarding this work.
  •  Please contact Adam Riggs at Adam.Riggs@jedunn.com with questions.

May 18, 2016 Update (From Lisa Smith)

West Pearl Streetscape Punch List Work

  • The city is conducting final punch list work on West Pearl between 8th and 11th streets from Wednesday May 18 through the end of the week and possibly next week if needed.
  • Concrete work will take place on the north and south sides of Pearl (again between 8th and 11th streets) at various locations.
  • The work sites will be small and while there may be temporary partial blockage work will not fully block streets, sidewalks or entrances.
  • We anticipate this being the final work for the city on the West Pearl Streetscape project.
  • Thank you for your continued patience.

 

February 17, 2016 Update (from Scott Pashman - JE Dunn)

PearlWest Project Update:

  • Temporary covered walkway on the south side of Pearl will be removed this weekend (February 20-21).  The sidewalk will be closed and all pedestrian traffic will be routed to the north side of the street. 
  • Fencing will replace the walkway (with gates for minimal construction traffic to come in and out).
  • Weather permitting, the sidewalk will be re-opened by CU graduation weekend in May.
  • Covered walkway adjacent to Centro will likely close at the beginning of March and remain closed until the end of March.  Every attempt will be made (weather permitting) to open the walkway back up sooner rather than later.
  • Around the beginning of April, the alley will be closed from the covered walkway to 11th Street.  The alley will be taken apart and put back together as quickly as possible.  PearlWest will contact businesses with alley parking spots.   There will be flaggers in the alley to help delivery trucks back out on 9th.
  • Also around the beginning of April, on Walnut the temporary covered walkway will be removed and fencing and a gate will be put up in its place.  The sidewalk pour on Walnut should go a lot faster and again, the entire sidewalk closure around the building should be wrapped up by CU graduation in May (weather permitting).
  • In March and April, other contractors will be starting internal build outs of their tenants properties which may mean some minor construction happening in the alley.  JE Dunn's portion (outside shell) is scheduled to be completely wrapped up by the end of May.
  • Click here to view a PDF map of the sidewalk closure.
  • If any businesses have questions/concerns during this time, please don't hesitate to find a JE Dunn representative onsite.

February 10, 2016 Update (from Kurt Mathews)

PearlWest Project Update:

The Pearl Street portion of this project is beginning to wrap up.  The tower crane that has been a fixture for months is about to come down.  Another crane will be brought in this weekend to complete the process.  This crane will be set up in the alley at the west end of the project (directly affected businesses have been contacted).  The crane will arrive early Friday morning (February 12) and set up will begin.  Once the new crane is in position, the removal of the tower crane will begin and should be completed on Saturday, February 13.  The new crane will then be disassembled and removed sometime on Sunday, February 14.  To accomplish this task, the alley will be closed east from the pedestrian walkway for the duration of the project.  Signage will be in place as well as flaggers.  The pedestrian walkway will remain open to foot traffic with temporary delays for safety reasons.

It is now time in the progress of the project to begin site improvement work (sidewalks, street, and plaza areas).  To accomplish this work it is necessary for safety  and traffic reasons to remove the covered walkway along the south side of Pearl.  All foot traffic will be moved to the north side of the street. Removal of the covered walkway will begin around 2/17/16.  It is anticipated that it will take at least two months to complete the site work and have a new sidewalk open to the public. The entire external part of the project is still on schedule for a May completion.  Interior finishing will continue once the exterior of the building is complete. The Walnut portion of the project is scheduled to be complete a couple of months following the Pearl Street portion.

January 6, 2016 Update (from Kurt Mathews)

Starting Sunday, January 10th at 5am 11th Street will be closed between Pearl and Walnut until Monday, January 11th at approximately noon.  

A large crane must be set up in order to place the heating/air conditioning unit on the roof of the PearlWest building.  (The current tower crane is not rated to lift the weight of the unit.)  

The full street is needed to allow assembly, placement, and disassembly of the crane unit.  It is anticipated that Sunday will be used for assembly and placement and Monday will be used to disassemble the crane.  If there are no unforeseen circumstances, the road should be open by noon on Monday, January 11th.  

Access to Lawry Lane will be available off of Broadway. The alley between 9th and 11th will be closed at the pedestrian walkway (10th Street).  The sidewalk along the east side of 11th will remain open to pedestrian traffic.  Thank you for your consideration and patience. The job is close to being finished. 

July 23 Stakeholder Meeting

Please click here for a recap of the August 1 Stakeholder Meeting

July 22 Update (from Molly Winter)

The West Pearl Streetscape Improvements project wraps up this month with the installation of six way-finding sandstone columns between 7th and 11th streets. Each column is inscribed with a poem submitted by a local poet. The winning poetry submissions were chosen from more than 60 entries expressing what the poet loves about urban life in Boulder. The poems selected for the columns were submitted in the following categories by these Boulder County poets:

Children/Youth category: Ruth Star
Amateur category: Valerie Hess and Susan Crane
Professional category: Ariella Ruth, Simon Fill and Carrie Host

Read press release here.

July 17 Update (from Kurt Matthews)

There will be a Community Meeting on Thursday, 7/23/15 from 12-1 p.m. at Centro Latin Kitchen to discuss updates/plans/progress:

JE Dunn will start placing concrete for the Walnut building in early August 2015 and will be substantially complete with that phase by late December 2015.  To achieve this schedule JE Dunn is planning for approximately one concrete pour day per week during this period. These pour days will result in a lane closure to the west bound lane of Walnut in the 1000 Block.  Flaggers will be in place to direct traffic, parking will remain as currently configured.  Per City of Boulder requirements, concrete activities will start early in the day to allow demobilization by approximately 9am.  At that point, JE Dunn will reopen all lanes of traffic on Walnut.  Additional pours of concrete will be required for vertical elements of the building, the they are not anticipated to cause any lane closures. JE Dunn will notify City of Boulder staff of scheduled pour dates and city staff will keep the west end businesses appraised. 

June 18 Update (from Kurt Matthews)

PearlWest:

The PearlWest project will soon begin going vertical.  For safety reasons, the pedestrian walkway will be enclosed in scaffolding to provide a walkway.  Erection of the scaffolding will be done between 6am and 9am to minimize impacts.  Work has begun on the Walnut site.  An area of parking and the sidewalk will be closed for safety reasons.  A walkway will be maintained similar to what is currently on Pearl.

April 2 Update (from Ashlee Herring)

PearlWest:

  • The concrete pour scheduled for today has been postponed until Monday, April 6 due to weather.
  • Additional pours are scheduled for April 10, and April 14 (weather dependent).  
  • There will be a constant parade of concrete trucks on those days starting early in the morning and continuing through the day.  Trucks are timed so that there should be no back up on 9th or in the alley.  
  • There will be no exit to 11th, the alley will remain open to those in the 900 block.

March 25 Update (from Ashlee Herring)

West End Streetscape:

  • Work has wrapped up in front of Lolita's.
  • Work will continue on the SW corner of 8th & Pearl through next week (mid-week).
  • Crews will then move to the SE corner of 9th & Pearl (mid-week next week).

PearlWest:

  • The first of several major pours of concrete took place last week.
  • Additional pours are scheduled for April 2, April 10, and April 14 (weather dependent).  
  • There will be a constant parade of concrete trucks on those days starting early in the morning and continuing through the day.  Trucks are timed so that there should be no back up on 9th or in the alley.  
  • There will be no exit to 11th, the alley will remain open to those in the 900 block.  
  • Excavation will be complete by the end of this week.

 

March 11 Update (from Ashlee Herring)

West End Streetscape:

  • Work had begun again since the snow has melted
  • Finishing work this week in front of University Bikes and Nick & Willy's.
  • Work will move to the south side of Pearl @ Lolita's and on 8th street next week.
  • Parking on the east side of 8th will be closed from  Pearl to Walnut, however the parking on the North side of Pearl will reopen (next week).
  • Work on the NW corner of 9th and Pearl is expected to be complete today. Stone work will begin at 10th & Pearl next.
  • A pedestrian detour at 9th and Pearl will be reopened today. Flaggers will remain on Pearl, but lanes will be open.

PearlWest:

  • The alley will be closed from the pedestrian walkway to 11th on Saturday March 14 and Wednesday March 18th.
  • Drilling will be taking place on Saturday, March 14.  Staff will be on hand to direct traffic in and out of the alley through the west entrance.
  • PearlWest will be pouring 1000 yds of concrete on Wednesday, March 18 (weather permitting) for the garage floor. Concrete trucks will be moving down the alley starting at 5:00 am at a rate of 6 per hour until the pour is complete (probably late in the day).  Those with parking in the alley will need to come in and out between the trucks.  Everyone should expect congestion.  

 

February 6 Update (from Ashlee Herring)

West End Streetscape

  •     Work will begin Monday, Feb. 9th on the northwest corner of 9th and Pearl.
  •  Work will continue on the north side as contractors make their way west to 8th.
  • They will the move to the south side, in front of Lolita's, moving westward.
  • Contractors will be using space on 8th street between Walnut and alley for staging.
  • Parking will also closed in front of University Bikes on Monday.

PearlWest

  •     The project is entering into the concrete pouring phase.
  •  The project requires a 61 ft concrete pump truck. The truck will be in the alley or on the Walnut site and will be pumping concrete into the Pearl site.
  • The alley will be closed from the pedestrian walkway to 11th while they are physically pumping concrete. It will be reopened in the evening. The construction schedule will dictate when it is appropriate to pour.
  • A tower crane remains on site. Safety protocols require a loud whistle when the tower crane is swinging. This may be heard during the day.

 

February 4 Update (from Ashlee Herring)

  • The City received delivery of the stone yesterday which is what was required before to start work again.
  •  The contractors are planning to start bringing out equipment, etc. next Monday, February 9th and then start construction.
  • Work will be starting in the NW corner of 9th/Pearl in front of University Bikes.
  • More details and a full update to follow once more information is received.

January 27 Update (from Ashlee Herring)

As a general update on Pearl West, the project is now scaling back excavation. Truck traffic will continue, but will be less frequent.

Alley Closure: A tower crane will be moved in to complete work on the Pearl West project February 2, 3, and 4, 2015. The alley will be closed from the pedestrian walkway to 11 street from the morning of February 2 until work is complete, the evening of February 4. No access will be permitted in the alley during this time. Please make alternate plans for the three days.

We thank you in advance for your help and cooperation

December 12 Update (Will Bohner - Deneuve Construction Services)
Re: The alley between Pearl and Walnut, and 9th and 11th Streets, and restricted access Saturday morning 12/13/14.

We will be pouring concrete from 5:00 am up until 7:30 am. (With luck, we will be completed by 7:00). Truck access to the alley from 9th Street will not be available. It is our intention to have the alley opened back up and all equipment removed by 7:30. Please plan your trash routes accordingly.

December 3  Update (from Ashlee Herring)

Streetscape Update:

  • Additional work was added to the scope of the project
  • Additional work includes more trees, brickwork, and sidewalk work
  • Work has been halted for the holidays
  • Work will begin again after the holidays at a date TBD and should take approx. 1 month to complete

PearlWest:

  • Excavation to resume on Monday. Truck traffic will return to the alley.
  • There will be a temporary closure of the alley while Comcast works in the alley. We will advise when we receive notice.
  • Drilling on the Walnut site will continue for the next couple of weeks.

909 Pearl:

  • Two concrete pours are planned
  • 12/4 between 5am and 9am
  • 12/11 or 12/12 between 4am and 7am

Both pours will require an alley closure

November 17  Update (from Ashlee Herring)

Streetscape Update:

  • The contractor has brought in a second crew to accelerate the work in an effort to minimize impacts during the holiday shopping season.
  • Work is expected to be complete this week on the south side of Pearl, between 8th and 9th.
  • Work has begun west of 8th on the south side of Pearl.
  • Sidewalk work continues on the SW corner of 9th and Pearl.
  • Brick is being installed in front of Past Jays.

Private Projects Update:

  • Pearl West: Excavation will continue into January.
  • 909 Walnut: Concrete pours are scheduled for Weds 11/19 and 11/26. Pours should be complete by 9:00am.

November 7 Stakeholder Meeting

Please click here for a recap of the November 7 Stakeholder Meeting

October 29   Update (from Brian Wiltshire)

Streetscape Update:

  • The work east of 9th is still anticipated to be complete by the end of next week. That includes replacing the temporary sidewalk with permanent brick and stone pavers, all of the benches, and the planter beds. We’re still waiting on Xcel to finish their work in front of Chipotle. They told us they’d be done by yesterday and it looks like they haven’t even started (it’s a two day operation). I should find out more today when they’ll be finished.
  • The kiosks are a separate contract and are currently being fabricated. They won’t be installed until January/February of next year.  
  • All of the parking will be restored before Thanksgiving week, and none of the fencing, cones, barricades, etc. will be left.
  • The contractor is not a month behind. The reason we added time to the contract is because we added a lot of work to the project (more replacement of curb and gutter, sidewalk, and changing tree grates to stone planter beds)
  • We’re doing everything we can to be finished by the holiday shopping season.

October 17  Update (from Ashlee Herring)

West Pearl Streetscape Project Updates

  • Crews are working on the planter beds, brick, and stone paving on the corner of 10th and Pearl for the next 1 ½ -- 2 weeks.
  • Crews will also be finishing up 11th & Pearl during this time period.
  • Work will then move back to 9th & Pearl.
  • Lane closures are in place between 10th and 11th.

Pearl West Update

  • Excavation for Pearl Street structure continues with increased truck traffic in the alley.
  • Excavation will then scale up the week of 10/20.

909 Walnut

  • Pier drilling will last a couple of weeks.
  • Coordination between The Daily Camera Site and the 909 Walnut Site continues. 

901 Pearl

  • Boring work is taking place under 9th Street

 

October 8  Update (from Ashlee Herring)

West Pearl Streetscape Project Updates

  • Crews are working on the planter beds, brick, and stone paving on the corner of 10th and Pearl.
  • Parking on the west side of 9th is expected to be open by tomorrow, once trees and irrigation are complete.
  • The pedestrian detour has been removed on the SW corner of 9th and Pearl.
  • Lane closures are in place between 10th and 11th.

Pearl West Update

  • Drilling for piers on Pearl Street expected to be complete Monday or Tuesday of next week.
  • Hauling of concrete and rebar will continue from Walnut site.
  • Excavation for Pearl Street structure expected to will begin next week with increased truck traffic in the alley.
  • Excavation will then scale up the week of 10/20.
  • Century Link continues to work on data lines in the alley.


909 Walnut

  • Excavation for structure is complete.
  • Pier drilling is beginning and will last a couple of weeks.
  • Coordination between The Daily Camera Site and the 909 Walnut Site continues.  

 
901 Pearl

  • Steel is being erected
  • Xcel will be on site next week to move overhead wires.
  • The project will require core drilling under 9th street to the west alley.

 

October 3 Stakeholder Meeting

Please click here for a recap of the October 3 Stakeholder Meeting

September 26 Update (from Ashlee Herring)

  • Our Oct. 3 meeting public information/business meeting will be held at RE/MAX Downtown Alliance, 1035 Pearl St., Suite 101B at 8:30am. Thank you to Jay Hebb and his team for making this available

West Pearl Streetscape Project Updates

  • Work is being wrapped up on the southwest corner of 9th and Pearl.
  • Crews will begin the planter beds, brick, and stone paving on the northwest corner of 10th and Pearl by next week. This will continue for the next two weeks.
  • Pedestrian detour remains in place for the SW corner of 9th and Pearl, but will be removed when work moves to 10th.
  • Daily lane shifts from 6am-3:30pm. Lane closures will be in place between 10th and 11th once work shifts.

PearlWest Update

  • Demo and haul off on the Walnut building will be complete on October 11th.
  • Drilling for piers on Pearl Street expected to be complete mid October.
  • Excavation for Pearl Street structure will begin on October 13th with a truck being loaded every 4 to 5 minutes.
  • Parking has been restored on Walnut side and sidewalk is now in use.
  • Overhead protection on Walnut will be removed on September 29th and 30th with work being done at night.

909 Walnut

  • Excavation for structure has began, trucks using same route as Daily Camera Site.
  • Water utilities have been stubbed into property.
  • Pedestrian walkway has been installed.
  • Coordination between The Daily Camera Site and the 909 Walnut Site continues.  

901 Pearl

  • All utilities have been installed into site.
  • Removal and under grounding of overhead power lines in alley will begin in approximately 2 weeks.
  • Crews continue to build structure.

 

September 22 Update (from Ashlee Herring)

  • Save the Date: Stakeholder Meeting:‚Äč Friday, October 3, 2014 | 8:30 a.m.  |  Location: RE/MAXX Alliance Downtown; 1035 Pearl St, Suite 101B

West Pearl Streetscape Project Updates

  • Work continues on the southwest corner of 9th and Pearl.
  • Next, crews will begin the planter beds, brick, and stone paving on the northwest corner of 10th and Pearl.
  • Pedestrian detour remains in place for the SW corner of 9th and Pearl.
  • Daily lane shifts from 6am-3:30pm.

PearlWest Update

  • PearlWest is wrapping up demolition of the old Daily Camera building.  Excavation will begin once demolition is complete.
  • Drilling is expected to continue through early to mid October.
  • The temporary pedestrian walkway on Walnut will be removed in the next week or so, and the parking returned on Walnut.
  • Once the construction reaches the point on the new building where safety dictates, the temporary walkway will return.

909 Walnut

  • 909 Walnut is getting ready to start.
  • Temporary walkways will be in place along Walnut and 4 parking spaces will be consumed during the duration of the project.
  • The contractors from 909 and Pearl West are in communication and are coordinating efforts to minimize impact.

901 Pearl

  • Structural steel is in place at the site
  • The temporary walkway will remain in place during this project

September 5 Stakeholder Meeting

Please click here for a recap of the September 5 Stakeholder Meeting

September 3 Update (from Ashlee Herring)

Monthly Meeting Update

  • Our next monthly Public Information meeting is schedule Friday, Sept. 5, 8:30am at Brasserie 1010.
  • We will be extending our monthly meetings thru October. The schedule will remain the same, first Friday in October at 8:30am.
  • We would like to identify a new location, west of 9th street, for this meeting to ensure the businesses most impacted in October have easy access.
  • Please let us know if you would be interested in hosting.
  • We extend a huge “THANK YOU” to Centro and Brasserie for hosting our monthly meetings since April.

West Pearl Streetscape Project Updates

  • Work continues to be focused on the southwest corner of 9th and Pearl for the next 2 weeks.
  • Work will move to the NW corner of this intersection once the SW is complete.
  • Trees on the SW corner of 9th & Pearl have been removed as of yesterday.
  • New curb and gutter, sidewalk, irrigation, brick, stone, tree planter beds, bike racks, and trash cans will be installed as the work progresses.
  • A pedestrian detour remains in place.
  • Daily lane shifts are in place at 9th & Pearl.

Pearl West Update

  • Work continues on the Walnut side of the building. This is expected to be complete by the end of next week.
  • Work will then move below grade.
  • Drilling will continue around the perimeter until approximately mid-October.

909 Walnut

  • Work is scheduled to begin on 909 Walnut mid-September.

 

August 28 Update (from Ashlee Herring)

West Pearl Streetscape Project Updates

  • Irrigation work is complete on the south side of Pearl.
  • Work has started west of 9th and will be focused on the southwest corner of 9th and Pearl for the next 2 ½ weeks.
  • Work will move to the NW corner of this intersection once the SW is complete.
  • New curb and gutter, sidewalk, irrigation, brick, stone, tree planter beds, bike racks, and trash cans will be installed as the work progresses.
  • There will be no work on Labor Day weekend.

PearlWest Update

  • Workers are continuing to drill the foundation piers. This is scheduled to continue through September.
  • The contractors are wetting down the site at the end of the day to mitigate the dust.
  • Demolition continues on the Walnut side of the building and is expected to continue for the next few weeks.
  • Work will continue on Saturdays until drilling is complete as an effort to shorten the duration of the drilling and move forward in the project.
  • Increase truck traffic will continue as debris is removed and concrete is poured.

Work is scheduled to begin on 909 Walnut mid-September. This project will put greater strain on the alley and will require coordination.

August 20 Update (from Ashlee Herring)

West Pearl Streetscape Project Updates

  • Only minimal work is being done this week due to CU Move-In
  • Some landscape work may be done during the week.
  • Work is scheduled to continue on the south side of Pearl between 9th and 10th next week.       
  • Finishing work on the north side of Pearl between 9th and 10th over the next couple of days.
  • Daily lane closures with directed traffic detours are in place in the 900—1000 block of Pearl.
  • Business access is being maintained at all times.

PearlWest Update

  • Continuing to drill the foundation piers.
  • Work will continue on Saturdays until drilling is complete as an effort to shorten the duration of the drilling and move forward in the project.
  • Work is finishing up on the west side, and should be moving to the east side.
  • Increase truck traffic will continue as debris is removed and concrete is poured.

909 Walnut Update

  • Work is scheduled to begin on 909 Walnut mid-September. This project will put greater strain on the alley and will require coordination.

August 8 Update (from Molly Winter)

We are always concerned about giving out interim completion dates because the perceptions about “completion” may be different  to different people and there are many things that can influence these dates.  We are constructing the west Pearl streetscape in smaller sections to minimize the overall impact to the businesses in the corridor.  The contractors work areas are generally limited block to block with the intent of minimizing visual and operational impacts to the businesses and minimizing lane closures that impact the vehicular traffic.  And, as we have discussed in past meetings, this project has many subcontractors to schedule that need to start and stop in each section and contractors are very busy therefore making scheduling very difficult.  And, if materials are delayed or one subcontractor is late, this has a ripple effect on all of the timing.

Pearl 11th to 10th
To date, we have finished the majority of the work in the block from 11th to 10th except for a small amount of work around the benches at both corners and we have finished most of the work at the intersection of 10th.  The remaining work in these areas includes the accent brick/stonework, planters, benches and landscaping at the corners.  We temporarily filled in some areas with a hard surface so that they can be open for pedestrian use in the interim and to minimize the visual impact of construction signing.  Once the stone/brick materials have been delivered and the subcontractor is on site, this work will be completed.

Pearl 10th to 9th
We are currently working in the block from 10th to 9th.  We completed the majority of the hard surface on the north side before starting the concrete removal on the south side; much of the parking is reopened on the north side and the sidewalk adjacent to the businesses is open to pedestrians.  The brick paving work is underway.  The remaining large opening on the north side of the street is where a planter will ultimately be constructed.

The projection was to complete the majority of concrete and asphalt (in the street) work in the intersection by the end of July which was met. The landscaped areas on both sides of the intersection are cordoned off; we are awaiting the delivery of buff sandstone which is later than we had anticipated due to the high demand for material in the construction industry. And we have always said that the stone monuments will be installed later in the project.  We are exploring ways with the contractor to place a temporary edger around the planters so that the barricading around the planters can be removed and some of the plant material installed, realizing that when the sand stone arrives it will need to be installed.  In the future we will be sure to clarify what work is yet to be completed before an area is totally finished.

We divided the south side of Pearl between 9th and 10th into two smaller areas to minimize the parking impacts understanding that the removal of parking is big concern for business owners.  The sidewalk and curb concrete is underway today in the first section to be followed by the second section.  After we complete this block, we will work on the 9th Street intersection and after that we will move to the construction west of 9th.  The work west of 9th is all in the amenity area between the curb and the sidewalk.

Accommodations that have been made for the businesses recently include on-going advertising, adding a banner at the west end of the mall, paying the contractor for overtime hours, moving stockpiles, staging areas, and portable toilets when requested and where it is possible, shortening work areas to lessen parking impacts, placing hard surface material to open sidewalks and to remove barricades and signage, minimizing work on the weekends, minimizing work in the late afternoons that impact patio customers, doing milling early on a weekend day and placing asphalt paving during early hours to be complete by the lunch hour, and trying to button up certain areas prior to the Ironman and minimizing work during the week before CU starts.

The benefits of the project in the end are to improve ADA access, repair damaged sidewalk, add amenities including irrigation, landscaping, tree grates, bike racks, benches, brick and stonework.  Hopefully the business owners will be happy with the streetscape for many years to come.

August 1 Stakeholder Meeting

Please click here for a recap of the August 1 Stakeholder Meeting

July 30 Update (from Ashlee Herring)

West Pearl Streetscape Project Updates

  • Finishing work on the north side of Pearl between 9th and 10th over the next couple of days.
  • Will move to the south side of Pearl between 9th and 10th Thurs. or Fri.
  • Will be working to open some parking on the north side of Pearl between 9th and 10th by late this week.
  • Daily lane closures with directed traffic detours are in place in the 900—1000 block of Pearl.
  • Pedestrian detour on the NW corner of Pearl and 10th should be opened by Thursday.
  • Will be coordinating with RTD for the new bus stop/ bus pad west of 10th and Pearl.
  • Xcel has finished work on the streetlight on the NW corner of 10th and Pearl.
  • Business access is being maintained at all times.

PearlWest Update

  • Scaffolding is being erected on Walnut with a temporary walk way diversion.
  • Demolition will continue on the Walnut building, with the façade starting to come down.  Once the building is down, scaffolding will be removed.
  • Xcel and Century link work continues in the alley.
  • Two large pieces of equipment were delivered on Tuesday morning, a third to come in on Monday.
  • Drilling will begin later this week or next for the foundation piers.

 
Our next monthly Public Information meeting is schedule Friday, August 1, 8:30am at Brasserie 1010. Invitation is attached.

July 23 Update (from Ashlee Herring)

West Pearl Streetscape Project Updates

  • Work will continue on the north side of Pearl between 9th and 10th for the rest of this week.
  • Concrete work in this area is expected to be finished by Wednesday of next week. Brick and stone work will follow.
  • Work on the south side of Pearl between 9th and 10th is expected to begin by the end of next week. This work will take 1-2 weeks to complete.
  • Daily lane closures with directed traffic detours are in place in the 900—1000 block of Pearl.
  • Business access is being maintained at all times.

PearlWest Update

  • The building facing Pearl Street is completely down and debris has been removed.
  • Demo continues on the Walnut building. One scaffold is in place. Brick work on the front is scheduled to begin.
  • Scaffolding is being installed on Walnut with a sidewalk detour being put in place. A scaffold tunnel is being built on the pedestrian path between the alley and Pearl.
  • Heavy equipment is being brought Monday and Tuesday of next week between 3:00—6:00 a.m.
  • Xcel will be working in the alley during the week.
  • Water hookup is scheduled for early next week.  This will impact the temporary walkway for a couple of days while trenches are dug and connections made.
  • Xcel is scheduled to begin night work in the alley next week, this will require closure.  JE Dunn is looking into measures to allow alley openings during the day.
  • Major drilling equipment and crane is now scheduled to arrive around Aug 4.

Our next monthly Public Information meeting is schedule Friday, August 1, 8:30 a.m. at Brasserie 1010.

Street Resurfacing Planned for Saturday, July 19 & Wednesday, July 23 (both early morning until noon).  Click here to learn more.


July 22 Update (from Kurt Matthews)

Click here to view the Traffic Control plan reflecting the proposed changes to convert the Alley to one-way traffic, starting from the Centro Walkway moving East…and the addition of the temp pedestrian walkway routing pedestrians around the demolition area on Walnut.  

JE Dunn's plan is to install the Walnut scaffolding and walkway at night the week of July 27th. The walkway would be in place for the remaining duration of structural demo of Walnut.  As for the one-way traffic in the alley, this would be implemented as soon as the alley is opened back up for thru traffic, likely following the Walnut structural demo.

July 18 Update (from Ashlee Herring)

  • We have a couple of updates from yesterday’s email…
  • The date for the paving has been changed to Wednesday, July 23 due to yesterday’s rain.
  • Work, with closures will be performed Saturday and Wednesday morning. Paving will take place next Saturday, July 19th on 10th Street north to the alley,  and the intersection at 10th and Pearl. Parking and streets will be impacted (closed) during this time, with the target of being reopened by noon.
  • Paving will take place next Wednesday, July 23nd on Pearl Street 11th—10th, the intersection of 10th and Pearl, and 10th Street north to the alley. Parking and streets will be impacted (closed) during this time, with the target of being reopened by noon.
  • Additionally, The walk way on the south side of Pearl, between 11th and 10th will be closed  Monday the 21st Thru Wednesday the 23rd for work on a 3” water line and vault installation on the south side of Pearl.


July 17 Update (from Ashlee Herring)

West Pearl Streetscape Project Updates

  • Work has moved to the north side of Pearl and will continue in this area for the next two weeks.  The bus pad area (south side 10th and Pearl) was targeted as the first place to install stone benches once they become available.
  • Half of the bike racks between 10th and 11th were installed last week.
  • Some temporary loading zones were removed on Pearl which were seeing little or no use.
  • Daily lane closures with directed traffic detours are in place in the 900—1000 block of Pearl.
  • Business access is being maintained at all times.
  • Normal work hours are 7:00am—3:00pm, though there may be some variance at times.
  • Work, with closures will be performed Saturday and WEDNESDAY morning. These were the only dates the asphalt company had available for the next couple of months. Click here to read the flier.
  1. Paving will take place next Saturday, July 19th on 10th Street north to the alley,  and the intersection at 10th and Pearl. Parking and streets will be impacted (closed) during this time, with the target of being reopened by noon.
  2. Paving will take place next Wednesday, July 23rd on Pearl Street 11th—10th, the intersection of 10th and Pearl, and 10th Street north to the alley. Parking and streets will be impacted (closed) during this time, with the target of being reopened by noon.

PearlWest Update

  • The building facing Pearl Street is completely down and debris has been removed.
  • Work continues at night in the Walnut facing building.  Most of that building is being torn down by hand (connecting walls).  S
  • Scaffolding is scheduled to be installed on Walnut side sometime next week.  A temporary walkway will be established similar to Pearl.
  • Water hookup is scheduled for early next week.  This will impact the temporary walkway for a couple of days while trenches are dug and connections made.
  • Xcel is scheduled to begin night work in the alley next week, this will require closure.  JE Dunn is looking into measures to allow alley openings during the day.
  • Major drilling equipment and crane is now scheduled to arrive around Aug 4.

901 Pearl

  • The alley will be closed behind 901 Pearl for at least one week for Excel work in the near future. Business access will be maintained. We will provide firm dates when we have them.

July 11 Stakeholder Meeting

Please click here  for a recap of the July 11 Stakeholder Meeting


July 8 Update (from Ashlee Herring)

General Information

  • Our next public information meeting is scheduled for Friday, July 11 at Brasserie 1010 at 8:30 am (note: new location).
  • Additionally, we will be holding a special field visit/walk through of the West Pearl Streetscape beginning at 7:45 am. We will be talking specifically about construction phasing and showing attendees work completed thus far. Please meet outside of Brasserie 1010 to join the tour.
  • The City of Boulder has received a letter from Downtown Boulder, Inc. (DBI) highlighting Action Steps the DBI board is requesting. The City has prepared and sent a response to DBI. Click here to read DBI's letter.  Click here to read the city's response.

West Pearl Streetscape Project Updates

  • Crews have finished the temporary infill in front of Salt, Pasta Jays, and Centro.
  • Work will then move to the north side of Pearl, west of 10th for the next two—three weeks.
  • Parking has been reopened on the west side of 10th street.
  • Bike racks have been received and will be installed on Pearl, between 10th and 11th by the end of next week.
  • Daily lane closures with directed traffic detours are in place in the 900—1000 block of Pearl.
  • Business access is being maintained at all times.
  • Working hours have been extended to 6:00 am—3:30 pm through this phase of the project.

PearlWest Update

  • Demolition has begun on the Walnut side, primarily interior work at this time.
  • Scaffolding will be going up on Walnut and in the 10th street walkway between Pearl and Walnut.
  • The alley will need to remain closed at least through the end of July.

 

July 2 Update (from Ashlee Herring)

West Pearl Streetscape Project Updates

  • Crews are finishing the temporary infill on the south side of 10th. Patio railings will be reinstalled in time for the holiday weekend
  • Work will continue on the west side of 10th this week. Work will then move to the north side of Pearl for the next two weeks.
  • Irrigation work is ongoing on 10th.
  • City staff are identifying locations for the installation of the new bike racks on 10th—11th. The bench being installed on 11th and Pearl is in fabrication. Both are expected to be installed within the next two weeks.
  • Daily lane closures with directed traffic detours are in place in the 900—1000 block of Pearl.
  • The pedestrian detour has been removed.
  • Business access is being maintained at all times.
  • Normal work hours are 7:00am—3:00pm, though there may be some variance at times.
  • No work will be performed Friday, July 4th—Sunday, July 6.

PearlWest Update

Demolition on the Pearl street side of the building is complete.
Crews are trucking debris out from the basement of the building.
Demolition work is now beginning on the Walnut side, primarily interior work at this time.
The alley will need to remain closed through the end of July.
Jersey barriers are place from 11th to the walkway to create a temporary pedestrian path.

 

Sidewalk repair projects scheduled west of Broadway to 8th, from Walnut to Spruce, have been delayed until 2015 to minimize construction and parking impacts.

 

June 25 Update (from Ashlee Herring)

West Pearl Streetscape Project Updates

  • Work is continuing on the bulb out on the north west corner of Pearl and 10th.
  • Work will then move west, between 9th and 10th.
  • Business access is being maintained at all times.
  • Daily lane closures with directed traffic detours are in place in the 900—1000 block of Pearl.
  • A pedestrian detour remains in place with a temporary crosswalk.
  • Normal work hours are 7:00am—3:00pm, though there may be some variance at times.

PearlWest Update

  • Demolition continues on the Pearl street side of the building.
  • Bridge Demo started 6/23 and targeting to be substantially completed by the end of the week.
  • The alley will need to remain closed through the end of July to allow for demolition and Excel/Century Link work.
  • Jersey barriers are place from 11th to the walkway to create a temporary pedestrian path.
  • Night work on Pearl has been completed.
  • Lane shifts will be in place tomorrow, 6/26 to allow for patching of asphalt.
  • Early morning work will occur this Friday, 6/27 4am-7am. Some parking will be impacted.

June 18 Update (from Ashlee Herring)

West Pearl Streetscape Project Updates

  • Work expected to be complete on the bulb out on the south side of Pearl and 10th by the beginning of next week.
  • Work will then begin on the bulb out on the north west corner of Pearl and 10th.
  • Work will then move west, between 9th and 10th.
  • Parking is open on the east side of 10th and in portions of the west side of 10th.
  • The mulberry tree on 9th street will remain in place. The removal of the Ash trees is still planned.
  • Business access is being maintained at all times.
  • Daily lane closures with directed traffic detours are in place in the 900—1000 block of Pearl.
  • A pedestrian detour remains in place with a temporary crosswalk.
  • Normal work hours are 7:00am—3:00pm, though there may be some variance at times.

PearlWest Update

  • Demolition continues on the Pearl street side of the building.
  • The alley will need to remain closed probably through the end of July to allow for demolition and Excel/Century Link work.
  • The fence will be moving into the roadway today, 6/18/14. The sidewalk and parking on Pearl south side will be taken from 11th to breezeway between the project and Centro.
  • Jersey barriers will be put in place from 11th to the walkway to create a temporary pedestrian path.
  • Pearl will need to be closed for water vault installation for two nights during the week of the 23rd. Pearl closures will be a night only, between 9:00pm and 7:00am.

June 13 Update (from Ashlee Herring)

West Pearl Streetscape Project Updates

  • Work will continue on the south side of Pearl at 10th street for the next 2-3 weeks.
  • Work will then move west, between 9th and 10th.
  • Parking is open on the east side of 10th and in portions of the west side of 10th.
  • A signal light moved at 9th street to prepare for the construction of a street park or “pocket” park area. Graphics of this intersection are attached to this email. Construction on this intersection will begin in August.
  • Business access is being maintained at all times.
  • Daily lane closures with directed traffic detours have begun in the 900—1000 block of Pearl.
  • A pedestrian detour remains in place with a temporary crosswalk.

Pearl West Update

  • Demolition is underway, the Daily Camera building (Pearl St. side) should be down by the end of the week/early next week.
  • The alley will need to remain closed probably through the end of July to allow for demolition and Excel/Century Link work.
  • The fence will be moving into the roadway on Wednesday 6/18. The sidewalk and parking on Pearl south side will be taken from 11th to breezeway between the project and Centro.
  • Jersey barriers will be put in place from 11th to the walkway to create a temporary pedestrian path.
  • Scaffolding will start to go up next week, to include the pedestrian walk way cover
  • Pearl will need to be closed for water vault installation for two nights during the week of the 23rd. Pearl closures will be a night only, between 9:00pm and 7:00am.
  • Some things will be happening in the next week or so, all dates are tentative and dependent upon demo status and permits.

June 11 - PearlWest Update (Kurt Matthews)

Dates below are tentative and dependent upon demo status and permits:

Wednesday, June 18 (approximately), the fence will be moving into the roadway - taking away parking spaces.  Jersey barriers will go in place to create the temporary walkway.

Sometime the week of the June 23, water line work will start.  They need to trench across Pearl to tap into the main line, and dig a vault in the sidewalk area of PearlWest.  The work is planned to occur at night with a start time between 9 and 11 pm and finish by 7 am.  Pearl Street will need to be closed between 11th and 10th during those work hours.  Plates will be put down to allow the street and parking to be open during the day.  This project should take only two nights.

June 9 - Tree Flier (Ashlee Herring)

Click here to download a flier that can be distributed to businesses, customers, and the public regarding the City’s tree replacement program.

June 6 Stakeholder Meeting

Please click here for a recap of the June 6 Stakeholder Meeting

June 5 Update (from Ashlee Herring)

West Pearl Streetscape Project Updates

  •  Work has begun on the south side of Pearl to finish intersection work.
  • This will be followed by work on the west side of tenth.
  • Work will then move west, between 9th and 10th. Business access is being maintained at all times.
  • Daily lane closures with directed traffic detours have begun in the 900—1000 block of Pearl.
  • A pedestrian detour remains in place with a temporary crosswalk.

Private Projects

901 Pearl:

  • Demolition continues on the 901 Pearl project. Temporary pedestrian access is being put in place at this site.

West Pearl Project:

  • The City is coordinating with contractors for the project to have business logos and/or art (murals) placed on the construction fencing around the project.
  • A crew will be on-site today (6/5/14) to finalize plans for demolition. Demo is expected to begin this afternoon or tomorrow morning.

Factors in the Replacement of 9th Street Ash Trees

  • Trees are in poor to fair condition.It does not appear irrigation is functional at this location.
  • These ash trees are at (short term) risk from emerald ash borer. EAB is (at most) 1 mile away from this location and probably already much closer.
  • The ash trees on 9th are below the City’s 10” diameter threshold for city EAB treatment so all pesticide applications are the responsibility of the property owner.
  • Pesticide treatments will need to be done for the life of the tree. Given the size of these trees it doesn’t coincide with our city goal to minimize pesticide use in the long term. The property as it currently is, a “by-right project” with no development history so we have no ability to require the property owner to replace street trees when those ash trees die from EAB.
  • We (Forestry) can’t replace those trees given the existing site conditions – lack of functional irrigation, 4’x4’ cut outs with the raised curb.
  • The ash trees on 9th St. exhibit signs of lilac/ash borer. Lilac/ash borer is a common insect pest of ash that tunnels through the sapwood causing crown dieback.
  • Previous damage from lilac/ash borer can also prevent uptake of systemic pesticides applied to control emerald ash borer.

Condition of Trees from City’s review

The trees along the west side of 9th from north to south are;

-          22” Mulberry in fair condition

-          5” White Ash in poor condition

-          6” White Ash in fair condition

-          5” White Ash in fair condition

-          10” Green Ash in fair condition

-          6” Green Ash in poor condition

-          8” Green Ash in fair condition

 

May 30 Update (from Ashlee Herring)

West Pearl Streetscape Project Updates

  • Work has moved to the 900—1000 blocks of Pearl.
  • Parking has been reopened on Pearl from 10th to 11th.
  • Business access is being maintained at all times.
  • Daily lane closures with directed traffic detours have begun in the 900—1000 block of Pearl.
  • A pedestrian detour remains in place with a temporary crosswalk.


Private Projects

  • 901 Pearl: Demolition continues on the 901 Pearl project. Temporary pedestrian access is being put in place at this site.
  • West Pearl Project: There have been some delays in the moving of a transformer in the alley, resulting in the alley remaining closed. Demolition will begin once the alley work is complete.

 

May 21 Update - Kurt Matthews

The Boulder Streetscape project is entering a phase that will impact the south side of Pearl (Centro, Trident, Wok Eat, Old Tibet & Classic Facets).  On Tuesday, May 27, the contractors are scheduled to start work on the bus pad located on the south side of Pearl at 10th.  I do not have all the details, but from what I know this involves removing asphalt and pouring a concrete pad where the buses will stop.  To do this work, we will need to divert traffic for a week.  (The bus pad in the west bound lanes on Pearl - hence the need for the lane shift.) This means we will need to create a traffic lane in the southern half of Pearl removing the parking lane, temp load zone and the bike corral temporarily.  Once the project is complete, we will return the parking, load zone, and bike corral. 

Also, as a further heads up, we have asked the contractor not to work on Friday this week allowing a 4 day Memorial Day weekend without construction.

May 16 Update - City of Boulder

The city’s communications team has updated their West End Improvements Web page to include the latest information and resources. Click here to view.

May 15 Update from JE Dunn Construction (PearlWest Contractors) re: Alley Parking Spaces

Attention businesses who have parking spaces in alley: JE Dunn Construction (PearlWest Contractors) has re-evaluated the alley access protocol and determined that the windshield stickers are not necessary and will be discontinued.  The original intent of the stickers was to minimize the inconvenience for the surrounding business owners and their employees, however they have resulted in added confusion.  JE Dunn has instructed Work Zone of the revised protocol and they will allow access to ALL personal vehicles regardless of stickers.  The only traffic control access restrictions will be limited to delivery and service vehicles.

May 8 Update (from Ashlee Herring)

As a reminder, the Pearl West project is scheduled to begin Monday, May 12. Alley restrictions and loading zones will be in place and enforced as of Monday. Please click here for a map showing specific zones.

April 29 Update (from Ashlee Herring)

UPDATED About temporary sidewalks: At 901 Pearl, the sidewalk needed to be closed for specific period of time to accommodate a crane to accomplish the demolition.  The demolition is complete. The closure ended May 6 and the pedestrian path was re-opened May 7th.

Regarding the PearlWest project, city staff met with the contractors and there will be a pedestrian walkway in front of the site to accommodate the pedestrians on the south side of Pearl from 11th to 10th.  Specific construction issues may impact the walkway for short periods. 

West Pearl Streetscape Project Updates

  • No work on the Streetscape Project 5/7—5/1l to accommodate graduation and Mother’s Day. Most pedestrian and vehicle detours are lifted during this time.
  • The first phase of the project, 10th—11th is on schedule.
  • Parking has been reopened on Pearl from 11th to Ozo.
  • Most restaurant patio railings in the 10th—11th block have been installed.
  • Work will continue next week on 10th and in the “bulb out” on the corner of 10th and Pearl. Work will then move up the east side of 10th, down the west side of 10th, and then the northwest corner of 10th and Pearl.
  • Business access is being maintained at all times.
  • Daily lane closures with directed traffic in 1000 block will continue beginning Monday, May 12.
  • A pedestrian detour remains in place with a temporary crosswalk.

Private Projects

  • Demolition continues on the 901 Pearl project. Temporary pedestrian access is being put in place at this site.
  • Work is scheduled to begin on the West Pearl project May 12.
     

May 2 Stakeholder Meeting:

Please click here to read the meeting recap from the May 2nd Stakeholder Meeting.  Also, please click here to view the Alley Management Plan (Site Logistics & Construction Traffic Flow Map).
 

April 29 Update (from Ashlee Herring)

West Pearl Streetscape Project

  • The first phase of the project, 10th—11th is on schedule to be complete by the end of the week.
  • Restaurant patio railings in the 10th—11th block, are being installed today and tomorrow.  Trees will be going in tomorrow in this same block.
  • Work will continue on 10th and in the “bulb out” on the corner of 10th and Pearl. Work will then move up the east side of 10th, down the west side of 10th, and then the northwest corner of 10th and Pearl.
  • Business access is being maintained at all times.
  • Daily lane closures with directed traffic in 1000 block will continue.    
  • A pedestrian detour remains in place with a temporary crosswalk.
  • Project will shut down Thursday, May 7—Sunday, May 11 for CU graduation and Mother’s Day. Pedestrian and vehicle detours will be lifted during this time.

Private Projects

  • Demolition continues on the 901 Pearl project.
  • Work is scheduled to begin on the West Pearl project May 12.

April 22 Update (from Ashlee Herring):

  • The sidewalk on the north side of Pearl, between 10th and 11th is open, but a pedestrian detour remains at the temporary crosswalk.
  • The first phase of the project, 10th—11th is on schedule to be complete by the end of next week.
  • Restaurant patio railings will be installed in the order they were removed, working west to east. Installation date is being determined at this time.
  • Work will continue on 10th and in the “bulb out” on the corner of 10th and Pearl.
  • Business access is being maintained at all times.
  • Daily lane closures with directed traffic in 1000 block will continue.    
  • Work has begun on the 901 Pearl project as well. Look for future updates on this project as work progresses.
  • Work is scheduled to begin on the West Pearl project May 12.

April 10 Update (from Ashlee Herring):

West Pearl Streetscape

  • Parking spaces are closed along the north side of Pearl Street between 10th and 11th streets.
  • The sidewalk on the north side of Pearl, between 10th and 11th is closed for concrete work.
  • Sidewalk work will move further west down Pearl, closer to 10th this week and next.
  • Work will continue in the intersection of 10th & Pearl.
  • Business access is being maintained at all times.
  • Daily lane closures with directed traffic in 1000 block will continue.    
  • Work has begun on the 901 Pearl project as well. Look for future updates on this project as work progresses.

April 4 Stakeholder Meeting:

Please click here to read the meeting recap from the April 4th Stakeholder Meeting.  Also, please click here to view the Alley Management Plan (Site Logistics & Construction Traffic Flow Map).

April 2 Update (from Ashlee Herring):

West Pearl Streetscape

  • Parking spaces are closed along the north side of Pearl Street between 10th and 11thstreets.
  • The sidewalk on the north side of Pearl, between 10th and 11th is closed for concrete work.
  • Business access is being maintained at all times.
  • Daily lane closures with directed traffic in 1000 block will continue.

March 26 Update (from Ashlee Herring):

West Pearl Streetscape

  • Parking spaces are closed along the north side of Pearl Street between 10th and 11th streets.
  • Access to adjacent businesses is being maintained at all times and a sidewalk on one side of each street will always remain open.
  • Lane closures with directed traffic on Pearl Street and 10th Street will continue.
  • Pedestrian traffic will switch to the street Thursday or Friday of this week. Will be working on only ½ block at a time.

March 20 Update (from Ashlee Herring):

West Pearl Streetscape

  • Parking spaces are closed along the north side of Pearl Street between 10th and 11th streets.
  • Access to adjacent businesses is being maintained at all times and a sidewalk on one side of each street will always remain open.
  • Lane closures with directed traffic on 1000 block will continue.
  • Work will begin on the 10th and Pearl intersection this week. Concrete will be poured later this week in the amenity zone.


March 11 Update (from Ashlee Herring):

West Pearl Streetscape

  • Contractors will begin re-paving later this week.
  • Sidewalks will start being poured next week. The plan is to work ½ block at a time.
  • Starting work on the intersection of 10th and Pearl next week.
  • The crosswalk on the western side of 11th and Pearl will be closed for a couple of days this week. Pedestrian traffic will be detoured to the mall side of 11th.

11th to 9th Alley Management Plan (Answers to questions asked at Friday’s meeting). (The alley plan focuses on the alley between Pearl and Walnut (or south side of Pearl).  The alley on the north side will be impacted by the project at 901 Pearl, but only occasionally as they need to do some utility work.  As those details and times become available we will notify businesses.)

  • The plan will go into effect after May 12, when work begins on Pearl West (old Camera building)
  • Parking spaces being designated as loading zones in the morning hours are chosen based on the number of businesses and the demand in the area. Blocks with more restaurants will have more spaces turned into loading zones in the morning hours.
  • Deliveries can be made in the alley before 6:00 am.
  • We have a message into Western Disposal and will have more information on their role in the plan soon.

Project Start Dates

  • 901 Pearl: Early April
  • 909 Walnut: Min June
  • PearlWest: After May 12

For complete Meeting Recap Notes, please click the PDF link on the right column of this page.  Highlights:

March 7, 2014 Update
  • City's Streetscape project started three weeks ago. Pedestrian access will move to street (bridge) entrances in about a week.  At this point, work will begin on sidewalks next to the buildings between 10th and 11th.
  • Alley Management Plan - Still working out a few logistics.  Proposed temporary loading zones from 6 a.m. - 11 a.m. at four locations (see meeting recap notes for more details).
  • City is working to get answers on some specific questions. More details about the alley management plan to be sent out soon.
  • PearlWest is still planning its start date mid-May as previously planned.
  • 901 Pearl is planning on a early April start date.
  • 909 Walnut's start date has been pushed back a few weeks from original plan.  Now looking like mid June.

March 4 Update (from Ashlee Herring):

West Pearl Streetscape Project Updates

  • Parking spaces are closed along the north side of Pearl Street between 10th and 11th streets.
  • Access to adjacent businesses is being maintained at all times and a sidewalk on one side of each street will always remain open.
  • Daily lane closures on Pearl (10th—11th) from 7:00am—4:00pm.
  • 11 street lane closure will be in place from Spruce to Pearl, Weds, 3/4—Thurs, 3/5.
  • Tear out and replacement of sidewalk continues on north side of Pearl (10th—11th).
  • Concrete scheduled to be poured on curbs and gutters this week.        
  • Hoping to pave parking area next week.

February 27 Update (from Ashlee Herring):

West Pearl Streetscape Project

  • Parking spaces are closed along the north side of Pearl Street between 10th and 11th streets.
  • Access to adjacent businesses is being maintained at all times and a sidewalk on one side of each street will always remain open.
  • Tear out and replacement of sidewalk continues on north side of Pearl (10th—11th).
  • Daily lane closures on Pearl (10th—11th) from 7:00 am—4:00 pm.
  • All bike racks from 10th-11th have been pulled from the north side of Pearl and are being reset on the south side.

Visit our webpage at www.westpearlupdates.com for FAQ’s, maps and graphics, and more information.

For complete Meeting Recap Notes, please click the PDF link on the right column of this page.  Highlights:

February 14, 2014 Update
  • City's Streetscape project begins Tuesday, February 18  (between 10th and 11th - north side).  (read city press release here)
  • No parking signs going up February 14 and will stay up for duration of this first phase between 10th and 11th.
  • Projected timeline for this first phase is February 18 - May 9 (goal is to be done with work on this block before CU Graduation).
  • PearlWest's start date has pushed back to May 12 to accommodate for CU Graduation / Mother's Day weekend.  Fencing will go up at that time.
  • Current tenants in the Walnut side of the PearlWest building will receive evictions notices around March 1 and will have to be out by April 15, 2014.
  • Demolition from Pearl Street to the alley will take about one month then demolition on the Walnut side will begin.
  • Work Schedule:  Streetscape Project: 7 a.m. - 4 p.m. (Mon. - Fri.) / PearlWest 7 a.m. to 5 p.m. (Mon. - Fri. and maybe occasional weekend.)
  • PearlWest is working with the city to possibly request a 6 p.m. stopping time - this has not been decided/confirmed. 
  • A note from Kurt Matthews on the alley management plan: At the meeting today we began discussion about managing the alley and removing any loading in the alley between 6 am and 6 pm.  To compensate for that we are looking at creating temporary loading zones (6am-11am) on Pearl, 9th, and Walnut.  We discussed, in a small group, about temporarily removing the bike corral in front of the Trident.  This will allow additional vehicle parking and more importantly, greater flexibility in creating loading zones.  If anyone has immediate feedback, please let me know ASAP as I need to make decisions soon.  My plan would be to return the corral when construction progress allows. (303-413-7320)
January 28, 2014 Update
  • Initial Stakeholder Meeting happened January 28.  (See right column for PDF recap.)
  • Project Timeline:
  • Streetscape (bond project) - start date: mid February.  Starting on sidewalk replacement on Pearl between 10th & 11th streets. Projected completion date of this block (Phase 1) early May.
  • PearlWest (Camera building) - start date: late April - fencing goes up.  Demo and construction to follow.
  • 901 Pearl (Tesla building) - start date: late March - demo.  Late April - construction starts.
  • 909 Walnut - start date: early May.

Streetscape Improvements Schedule - as of January 30, 2014 - For additional details, visit the city's website.

Phase Section Schedule Improvements
One 10th to 11th streets Mid-February 2014 to May 9, 2014. Sidewalk replacements
Two

9th/Pearl streets intersection
10th/Pearl streets intersection

Mid-April 2014 to August 2014 Pedestrian crossings and curb extensions
Three Pearl Street from 7th to 11th streets Late August 2014 Street tree replacement

 

The city will be installing:

  • a raised pedestrian crossing and curb extensions at the intersection of 10th and Pearl streets;
  • a curb extension at the southwest corner of the intersection of 9th and Pearl streets;
  • wider sidewalks for improved pedestrian movement and additional patio seating;
  • kiosks and wayfinding elements (totems) to establish a sense of direction and place on the "West End;"
  • new bus stops on eastbound and westbound Pearl Street;
  • new street trees, grates and irrigation systems;
  • Americans with Disabilities Act (ADA) sidewalk access improvements; and
  • other sidewalk amenities and pedestrian enhancements between 7th and 11th streets.

Downtown Commercial District Improvements
(City Site)

Click here for PearlWest Live Streaming Video

Contacts:

For construction, parking and/or alley management inquiries, contact:
Kurt Matthews
(Department of Community Vitality )
303-413-7320
matthewsk@bouldercolorado.gov

For PearlWest inquiries, contact:
Dan Schuetz
(Nichols Partnership)
303-291-2215
dan@nicholspartnership.com

Learn more about the PearlWest Project here.
 

Quick Links
Tree Replacement FAQ Flier
Temporary Loading Zone Map
Site Logistics & Construction Traffic Flow Map
FAQ (PDF) - will be updated regularly
Map of West Pearl Improvements
West Pearl Improvements Graphics
PearlWest (Daily Camera Building) at 1048 Pearl St.

Stakeholder Meeting Recaps:

November 7, 2014
October 3, 2014
September 5, 2014
August 1, 2014
July 11, 2014
June 2, 2014
May 2, 2014
April 4, 2014
March 7, 2014
February 14, 2014
January 28, 2014

Click here to view Inside Boulder News segment on city's streetscape work (February 21) - 1 minute
Click here to view Inside Boulder News segment (February 28)  - 6 minutes

Exciting things are happening on the West End: 

 

 

Subscribe

Keep up with events, promotions, openings and sales.

Downtown Boulder/1942 Broadway, Suite 301/Boulder, CO 80302
Phone: 303.449.3774/Fax: 303.449.1582